VIVAnews - PT Aneka Tambang Tbk. (ANTM) announced that they would accelerate the optimisation execution of Fero Nikel III factory sometimes in May which was previously scheduled on July 2009.
It was stated by Antam's secretary corporate Bimo Budi Satriyo in a written statement on Tuesday night, April 21. The acceleration plan was made after the company's consideration on nickel market condition which was expected to get better in the end of 2009.
Therefore, Antam will take advantage of nickel stable price to execute the factory optimisation. "In the end of the year, it's expected to have maximum operation of the FeNi III factory," as stated by Satriyo.
The optimisation acceleration is necessary because of indication and signs of leak in the furnace wall at a weak fire-proof level bricks found in April 18. At present, FeNi III factory operation has been stopped for cooling, and the company expects the factory can be discharged in May 2009.
--
Translated by: Ariyantri E. Tarman
VIVA.co.id
29 Maret 2024
Baca Juga :
Komentar
Topik Terkait
Jangan Lewatkan
Terpopuler
Selengkapnya
VIVA Networks
PT Suzuki Indomobil Sales (SIS) telah menyiapkan layanan Bengkel Siaga untuk mobil dan sepeda motor yang tersebar di 66 titik guna menyambut mudik lebaran 2024.
Istilah "insecure" erat kaitannya dengan tingkat percaya diri seseorang, yang merupakan perasaan yang dapat berubah sesuai dengan situasi yang dialami. Apakah ini dosa?
YouTuber asal Korea Selatan yakni Tzuyang datang ke Indonesia dan mukbang di beberapa tempat makan, salah satunya di tempat makan kaki lima kawasan Menteng, Jakarta Pusat
21 Tahun Lalu Diboikot Rhoma Irama, Inul Daratista Tetiba Ungkit Soal Baju buat Goyang Ngebor
JagoDangdut
28 menit lalu
Sudah 21 tahun berlalu sejak peristiwa ia diboikot Rhoma Irama. Inul Daratista kembali menjadi sorotan setelah memamerkan baju ngebor yang membuat kontroversi
Selengkapnya
Isu Terkini